METHOD STATEMENT FOR ELECTRICAL WORKS

METHOD STATEMENT FOR ELECTRICAL WORKS
METHOD STATEMENT FOR ELECTRICAL WORKS 


This Method Statement outlines the procedures for electrical works to be undertaken by RAMSPROZONE. The document details the steps involved in ensuring the safe, efficient, and high-quality execution of electrical tasks.
This Method Statement serves as a guide for personnel involved in the project, including electricians, supervisors, and inspectors. It ensures everyone adheres to the same standards and fosters clear communication throughout the project.

TABLE OF CONTENTS 

2.0. SCOPE OF WORK
3.0. REFERENCES
4.0. TOOLS & EQUIPMENT
5.0. RESPONSIBILITY
6.0. PROCEDURES
7.0. METHODOLOGY
8.0. TESTING AND COMMISSIONING. (REFER TO THE ATTACHMENTS)
9.0. QUALITY CONTROL
10.0. SAFETY REQUIREMENTS
11.0. REFERENCES
12.0. ATTACHMENTS

1.0. PURPOSE

The purposes of the Method Statement specify the requirements and procedures for the installation of Electrical Works in the above-mentioned project.

2.0. SCOPE OF WORK

The purpose of this method statement is to describe the procedure and methodology to be adopted as a part of Electrical fittings installation for the above-mentioned project. This document should be read in conjunction with the Project Quality Plan and Contract Specifications.

3.0. REFERENCES

3.1. Approved shop drawings
3.2. Local Authority Guidelines and Regulations Contract specifications and documents

4.0. TOOLS & EQUIPMENTS

4.1. Spirit level
4.2. Measuring Tape
4.3. Chalk line & powder
4.4. Wire Cutter.
4.5. Megger Meter
4.6. Tester
4.7. Drilling Machine
4.8. Grinding machine
4.9. Hydraulic Crimping Tool
4.10. Ladder or scaffolding with platform
4.11. Extension wire for Electrical power, etc.

5.0. RESPONSIBILITY

Being a leader of the MEP Team. The project Manager will be overall responsible for all MEP activities, including these above-mentioned Installation activities.

5.1. Project Manager

5.1.1. Have full authority and overall responsibility to manage, supervise, and control the works and have direct responsibility for ensuring safe working practices and compliance with regulatory authorities' requirements, coordinate with engineers for the execution of the Contract Scope of Works. 
5.1.2. Implement the project quality systems to the satisfaction of the project requirements.
5.1.3. Review changes and variations to evaluate the impact of those on time and schedule.

5.2. Project / Site Engineer:

Overall site supervision shall be the responsibility of the Supervising Engineer, who will oversee all works about the ascribed method statement. The project Engineer/supervisor will be responsible to:
5.2.1. Ensure that the works are carried out according to the Contract Specifications approved method statement and shop drawings.
5.2.2. To provide all necessary information and distribute responsibilities to his construction team.
5.2.3. Tool Box Talks are performed
5.2.4. Work Method Statement is communicated to the workers performing the scope of work.
5.2.5. Review Risk Assessment for compliance Communicate the Risk Assessments to the foreman.
5.2.6. Health and Safety inspections are performed
5.2.7. Work inspection - Issuing notification to the client-appointed Supervising Engineer for inspection and clearance.

5.3. QA/QC Engineer

5.3.1. Responsible for monitoring and making sure the works are in fulfillment with the specified requirements, and that all quality records related to the works are complete.
5.3.2. Ensure that all installations to be done are as per approved material, approved layout shop drawing and coordination drawings, approved installation details, and approved mock-ups.
5.3.3. Coordinate and carry out all the inspections with the MEP Coordinators QA/ QC Engineers and Consulting Engineers.

5.4. Safety Officer

Before commencing any activity, we will ensure that there will be safe access to the work site and a safe place for the execution of work.
5.4.1. The labor force shall receive a toolbox talk on the project site safety regulation. Any process that is adopted that may have a particular safety risk will be assessed and addressed as required.
5.4.2. Ensure that the proper PPE (safety shoes, helmet, hand gloves, reflected jacket, hand gloves, welding mask, etc.) and safety work permits are available before commencing any activities at the site.
5.4.3. The Designated safety officer shall have full authority to remove personnel from the operational areas and/or suspend the work activities should any personnel not be observing defined safety procedures.

5.5. Foreman / Supervisor

The designated Foreman will be accountable to the Supervising Engineer and shall be responsible for the efficient organization & control of the assigned operatives and scribed work activities.
5.5.1. Review Risk Assessment for compliance.
5.5.2. Communicate the Risk Assessment
5.5.3. Communicate Tool Box Talks as required and return the signed document to the Supervising Engineer.
5.5.4. Work Method Statement is communicated to the workers performing the scope of work.
5.5.5. Health and safety inspections are performed.

5.6. Storekeeper

Ensure that the materials delivered to the site shall be as per the material approval.
5.6.1. Check that the material quantity received against the order.
5.6.2. Check that the material received has proper documentation.
5.6.3. Ensure that the proper storage and identification shall be provided and maintained as per the manufacturer's recommendations.
5.6.4. Ensure that the material inspection has been carried out before installation.

6.0. PROCEDURES


6.1. MATERIALS


In compiling this method statement, it has been assumed materials to be used in the defined process will have been subjected to an approval process and subsequently approved by the client’s appointed representative as per the contract.

6.2. DRAWINGS

6.2.1. Prepare the workshop drawings showing a complete installation along with section details & obtain consultants' approval.
6.2.2. Prepare the co-ordination Drawings with other MEP works.
6.2.3. Obtain required approval on Electrical workshop drawings after the consultant’s approval.
6.2.4. Sub-station room trench layout and exact location of sleeves shall be obtained from the local authority (s).

6.3. Precautions / Actions:

6.3.1. All materials received at the site will be handled and stored properly. An inspection request will be issued for material inspection upon receipt.
6.3.2. Any damage, miss, and other discrepancies will be recorded and notified to the concerned. Any materials found not suitable for the site will be removed from the site and actions will be taken

7.0. METHODOLOGY


7.1. WORK METHODOLOGY & SEQUENCE OF WORK


7.1.1. Fixing conduits in the slabs.
7.1.2. Fixing conduits with GI boxes in the columns.
7.1.3. Fixing conduits with GI boxes in the walls.
7.1.4. Fixing Enclosures for Distribution Boards.
7.1.5. Wiring for lighting, & Power Points.
7.1.6. Fixing Cable Tray/Ladder.
7.1.7. Laying of L.V. feeder Cables.
7.1.8. Fixing D.B & SMDB Modification
7.1.9. Fixing wiring accessories & Light Fixtures.
7.1.10. Telephone / Data System.
7.1.11. Fire Alarm System.
7.1.12. Low Current System.

7.2. Conduits in the Slabs.

In this stage, we have to start our work directly after fixing the shatter, since there is a lot of work to be done before fixing the steel, Determine the exact placement of lighting fixtures, power outlets, and fire alarm points. Secure junction boxes at designated locations to house electrical connections.
Drill the necessary holes to accommodate electrical conduit leading to switches, bells, and break-glass pull stations. And DB’s. After finishing the steelwork, we will start fixing our conduits as per the approved shop drawings, of course, we have to avoid passing the conduits in the wet areas, minimize conduit bends, and securely fasten them to the steel structure. Utilize expansion couplers at locations with expansion joints.
At the end, we will use masking tape to close all the end openings of the conduits.

7.3. Fixing Conduits and GI boxes in the columns.

Before casting any column in the site, we have to check if there is any Switch Socket, bell, or broken glass fixed on the column. If there is any, we have to fix the GI or PVC box properly so that it will be touched with the shatter. Conduit installation within the column will be extended to the top.

7.4. Fixing Conduits and GI boxes in the walls.

Upon completion of masonry work on each floor, we will proceed with marking the designated locations for electrical devices (switches, sockets), telecommunication (telephone outlets), and entertainment (TV outlets). This will be done by the approved construction drawings. Then we will start chasing and chipping the marked locations by using the grinder, accordingly, we will fix the GI boxes with a minimum of 5 mm away. We'll ensure the GI boxes are positioned flush with the wall surface before plastering. The following day, we'll complete the conduit terminations by connecting them to the GI boxes."

7.5. Fixing DB’s Enclosures.

Usually, we always inform the main contractor, before starting the block work to use a block of 200 mm. width instead of 100 mm. and to locate plaster level points only in the location where recessed DBs, so that we can fix the enclosures properly and ensure the enclosures are completely flush with the plaster. The mounted height of the enclosures will be 1300 (bottom of the panel).
The distribution board will be aligned, leveled, and securely fastened to the wall.
The surface-mounted panel boards will be fixed at least 25 mm from the wall: ensuring supporting members do not prevent the flow of air.
Distribution board interiors will not be installed in cabinets until all conduits and Connections to the cabinet have been completed.
Trim for flush-mounted cabinets will be installed in a plaster frame, flushed with the furnished wall. Trim will be installed plumb and square to finish the paintwork.


Download File Now

Post a Comment

0 Comments